Suburban Chicago College Adds Technical Education Center

Aug. 1, 2009
Sustainability plays key role in design of this LEED facility

With an enrollment of approximately 31,000 students per semester and a 273-acre main campus, the College of DuPage (COD) ranks third among the nation's largest single-campus community colleges. To ensure it continues to meet community and student expectations, the Glen Ellyn, Ill.-based school is undergoing a $300-million renewal. Part of this upgrade includes construction of a $50-million, 177,000-sq-ft technical education center to house the architecture, automotive technology, computer-aided design, construction management, electro-mechanical technology, electronics-integrated engineering technology, HVAC/R, interior design, manufacturing technology, ornamental horticulture, and welding technology programs.

“The technical center was designed to be used as a teaching tool,” explains Jeff Leesman, P.E., LEED® AP, lead electrical engineer for Rock Island, Ill.-headquartered KJWW Engineering, consulting engineers for the project's mechanical, electrical, plumbing, fire protection, and structural & technology systems. “For example, MEP systems were purposefully left exposed in the shop areas. In classrooms and corridors, a floating ceiling grid was employed, allowing students to view the systems located above.”

In addition, the building's electronics labs are designed for hands-on demonstration. A common lab service room includes the suite's electrical connections with real-time power monitoring/metering for student interaction.

“Conduit infrastructure installed throughout the suite enables hands-on demonstration of networking,” adds Leesman. “There are even pathways to the roof for connecting satellites and antennas.”

Like many new buildings today, the technical education center incorporates various sustainable elements, including a 1,100-ton chiller plant with VFO-controlled compressors and a condensing boiler plant. Other energy-saving features include the widespread use of low-mercury T8 lamps as well as daylight/occupancy sensors and lighting controls that are integrated into a centralized building automation system.

According to Leesman, constructing the facility to LEED specifications proved to be challenging.

“The biggest obstacle KJWW faced was satisfying the programmatic requirements while meeting the client's sustainability goals,” he says. “This is because many of the technical program's space requirements go against being sustainable. Take the welding shop, for instance. This area requires light levels greater than 100 fc and extensive exhaust. To control energy usage, we equipped all 32 welding booths with an individual snorkel arm exhaust with integral task lighting and automatic arc sensing to control the dust collection system VFD.”

In addition, the building features a 30-bay automotive lab and four “drive-in” automotive classrooms, which not only required power, data, and compressed air to be supplied to each service location, but also in-floor vehicle exhaust systems, in-ground dynamometers, and in-ground auto lifts with lighting set into the floor slab to illuminate the underside of automobiles.

Another challenge included integrating flexibility into the HVAC, construction, and manufacturing labs, which KJWW overcame by installing extensive overhead electrical track busway systems that can power any piece of equipment in any location, regardless of voltage, phase, or load requirements.

“This adds to the building's sustainable goals, because it negates the need to add or remove conduit and wiring when equipment changes are made,” Leesman notes.

Despite these challenges, the COD technical education center opened on time for fall 2009 classes.

“This building is an engineer's dream,” says Leesman. “Designing and building each program's space was a project within itself.”

About the Author

Stefanie Kure | Content Producer - EC&M

Stefanie Kure is the senior associate editor of EC&M magazine. She holds a Bachelor of Arts degree from the University of Kansas and has more than 20 years of experience in the B2B magazine industry. In addition to EC&M, Stefanie has worked on Transmission & Distribution World magazine, Broadcast Engineering magazine, and Power Electronics Technology magazine.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

Electrical Conduit Comparison Chart

CHAMPION FIBERGLASS electrical conduit is a lightweight, durable option that provides lasting savings when compared to other materials. Compare electrical conduit types including...

Fiberglass Electrical Conduit Chemical Resistance Chart

This information is provided solely as a guide since it is impossible to anticipate all individual site conditions. For specific applications which are not covered in this guide...

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.