Insulation Resistance Testing, Part 5

April 20, 2010
Sometimes, an insulation resistance (IR) testing program is in place, yet a major cable failure still occurs

Sometimes, an insulation resistance (IR) testing program is in place, yet a major cable failure still occurs. Because it doesn't seem to work, cutting back or eliminating the program appears to make sense -- that is, until you look deeper.

In these situations, what hasn't happened is consistent testing followed by consistent trending. What makes an IR program work is the ability to trend data over time. A proper trend can't exist unless you do the same tests the same way on the same schedule every time. The only variation in the testing should be temperature adjustment, which also must be done in a consistent manner.

Figure out ahead of time what the testing interval will be for a given type of equipment, and stick to that interval. If you don't, then the program will fail as will your equipment. To determine that interval, you must balance a realistic level of access (and required downtime) against the minimum testing frequency that will allow you to detect insulation deterioration in a timely manner.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.

Champion Strut Catalog

Champion Fiberglass is the most advanced manufacturing facility of fiberglass conduit, fiberglass bridge drain and fiberglass strut systems in the world. Its well-trained and ...

8 Types of Electrical Conduit and Their Uses

Electrical conduit is a tube or raceway used to house and protect electrical wires within a building or structure. From data centers to underground subways to ports and bridges...

Strut Corrosion Guide

Learn how Champion Strut™ benefits projects with corrosion resistance.