Fill in the blank with the appropriate answer.

When installing communication wires and cables in cable routing assemblies, vertical runs of the cable routing assemblies shall be supported at intervals not to exceed _______, unless listed for other support intervals, and shall not have more than one joint between supports

A)  2 ft

B)  3 ft

C)  4 ft

D)  10 ft

Find the Answer

Answer: C

The installation methods of communications circuits installed within buildings are outlined in Part V of Art. 800. As noted in Sec. 800.110(C)(2), when installing communication wires and cables in cable routing assemblies in vertical runs, supports shall be installed at intervals not to exceed 4 feet, unless listed for other support intervals, and shall not have more than one joint between supports.

Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states. He can be reached at [email protected].

About the Author

Steven Owen

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.

8 Types of Electrical Conduit and Their Uses

Electrical conduit is a tube or raceway used to house and protect electrical wires within a building or structure. From data centers to underground subways to ports and bridges...

Champion Strut Catalog

Champion Fiberglass is the most advanced manufacturing facility of fiberglass conduit, fiberglass bridge drain and fiberglass strut systems in the world. Its well-trained and ...

Considerations for Direct Burial Conduit

Installation type plays a key role in the type of conduit selected for electrical systems in industrial construction projects. Above ground, below ground, direct buried, encased...