NEC in the Facility

July 21, 2009
If you have ignitable fibers on site, you can choose the zone classification system (Art. 506) as an alternative to the division classification system (Arts. 500, 502, and 503).

If you have ignitable fibers on site, you can choose the zone classification system (Art. 506) as an alternative to the division classification system (Arts. 500, 502, and 503). Although this initially seems like a good choice, beware: There’s no free lunch.

In 506.4(A), a short sentence requires the area in question to be "properly documented." The NEC doesn't clearly define this. Generally, all electrical installations must be properly documented. The problem is the opinion of "proper" varies.

Before deciding on a zone or division classification system, discuss the documentation requirements with your insurer. You may need additional resources to create and maintain what's required.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.

8 Types of Electrical Conduit and Their Uses

Electrical conduit is a tube or raceway used to house and protect electrical wires within a building or structure. From data centers to underground subways to ports and bridges...

A Powerful Duo: Fiberglass conduit and solar applications

Learn how strong, durable fiberglass conduit excelled in an environment with dense cable and helped make a complex burial much simpler for the contractor to help this customer...

Champion Fiberglass® Conduit Protects Cabling For New York's First Offshore Wind Farm

Learn how fiberglass conduit supported a heavy cable load and a buried installation to help this project reach a successful outcome.