Electrical Troubleshooting Quiz - September 22, 2015

Sept. 22, 2015
Why does the m otor, which is under PLC control, seem to “konk out?"

A motor drives a pellet feeder system to a reactor tank, which is supposed to output a batch every 20 minutes. But sometimes an hour goes by with no output. The motor, which is under PLC control, seems to “konk out.” The plant manager, in his current position only six weeks, is understandably nervous. He said, “Either fix the PLC logic or replace the motor. It has to be one of the two.”

What’s your next step?

With all due respect to the plant manager, it’s probably neither. Your next step should be the first step in troubleshooting a PLC-controlled system: check the final control element(s).

If that drain valve is sticking, for example, its limit switches won’t provide the signal that the drain cycle has occurred. So the PLC won’t tell the motor to provide more material for the next batch; this one’s still in the vessel.

If the valve is OK, check the limit switches. Maybe work this system backwards from the final control element(s) to the PLC, and keep going until you’ve addressed everything on the output side. Then look at the input side.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

8 Types of Electrical Conduit and Their Uses

Electrical conduit is a tube or raceway used to house and protect electrical wires within a building or structure. From data centers to underground subways to ports and bridges...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.

A Powerful Duo: Fiberglass conduit and solar applications

Learn how strong, durable fiberglass conduit excelled in an environment with dense cable and helped make a complex burial much simpler for the contractor to help this customer...

Champion Fiberglass® Conduit Protects Cabling For New York's First Offshore Wind Farm

Learn how fiberglass conduit supported a heavy cable load and a buried installation to help this project reach a successful outcome.