Question: True or false? The insulating bushing required to protect #4 or larger conductors in a raceway can be installed after the conductors are installed in the raceway to prevent damage to the bushing.

See answer below.

 

 

 

Answer: False.

Explanation: A revision to Sec. 300.4(G) makes it clear that one of the methods listed in Sec. 300.4(G) (1 - 4) must be in place before the conductors are installed.

Lupacchino is a senior design engineer with Gaylor Electric, Inc. in Noblesville, Ind. and serves as an alternate on NEC Code-Making Panel No. 3. He is currently licensed in more than 80 jurisdictions. He can be reached at [email protected]

About the Author

John Lupacchino | Senior Design Engineer

John began his career in electrical construction as an apprentice and worked his way through the trade. He is currently licensed in more than 80 jurisdictions. With more than 35 years of experience, he now plays a vital role in Gaylor Electric’s Engineering Department, where he serves as a senior design engineer. With a focus on design engineering, quality assurance, and code compliance, he has earned the highest level of respect from industry professionals alike. John currently serves as an alternate on NFPA 70 Code Making Panel No. 3. In addition, he enjoys sharing his electrical knowledge through education. As an Associated Builders and Contractors instructor, he continues to help grow a new generation of high-performing construction leaders.

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations