    To detect deterioration, insulation resistance testing should be conducted over time.
    Aug. 22, 2016
    2 min read

    Insulation resistance (IR) testing is widely used to assess the condition of insulation in such things as service cables, feeder cables and the wiring in major branch circuits. It’s also used to assess the condition of motor winding insulation.

    The problem is that an IR test taken in isolation seldom tells you anything useful unless the value is really low (as in almost no resistance). When a motor supplier states an IR testing value or range for maintenance purposes, that’s really just a guide for you to use in your baseline testing, prior to placing the motor in service. Unless the winding insulation is severely damaged, whatever value you get for that motor is the value that goes into the test data history of that motor.

    Notice, “test data history” not “PM procedure.” Why is this? Because to correctly assess the condition of the winding insulation, you are looking for deterioration. And that happens over time. Thus, it’s not that the test tech takes a reading and can tell that the winding insulation is deteriorating.

    It’s that someone “in the back office” must review the data in the computerized maintenance management system (CMMS) or motor maintenance software and look at the trend. A small deviation downward over time is normal, but if the curve suddenly “breaks downward,” you need to schedule that motor for service or replacement.

    If the motor is critical, you should conduct IR testing more frequently (if possible) or consider an automated system that performs this test.

    Winding deterioration also means the motor may draw more current to do the same work (depending upon how bad that deterioration is), so you can also monitor the current on each phase. This can be useful as a condition alert. For example, if one phase starts pulling more current relative to the other two, you may have a phase-to-frame fault developing.

    About the Author

    Mark Lamendola

    Mark is an expert in maintenance management, having racked up an impressive track record during his time working in the field. He also has extensive knowledge of, and practical expertise with, the National Electrical Code (NEC). Through his consulting business, he provides articles and training materials on electrical topics, specializing in making difficult subjects easy to understand and focusing on the practical aspects of electrical work.

    Prior to starting his own business, Mark served as the Technical Editor on EC&M for six years, worked three years in nuclear maintenance, six years as a contract project engineer/project manager, three years as a systems engineer, and three years in plant maintenance management.

    Mark earned an AAS degree from Rock Valley College, a BSEET from Columbia Pacific University, and an MBA from Lake Erie College. He’s also completed several related certifications over the years and even was formerly licensed as a Master Electrician. He is a Senior Member of the IEEE and past Chairman of the Kansas City Chapters of both the IEEE and the IEEE Computer Society. Mark also served as the program director for, a board member of, and webmaster of, the Midwest Chapter of the 7x24 Exchange. He has also held memberships with the following organizations: NETA, NFPA, International Association of Webmasters, and Institute of Certified Professional Managers.

    Voice your opinion!

    To join the conversation, and become an exclusive member of EC&M, create an account today!

    Sponsored Recommendations

    Sign up for EC&M Newsletters
    Get the latest news and updates.

    Latest from Test & Measurement

    ID 131895857 © Vichaya Kiatyingangsulee | Dreamstime.com
    dreamstime_xxl_131895857
    Strategic acquisition enhances Shermco’s Southeastern footprint with expanded operations near Birmingham
    ID 107048344 © Bayurov | Dreamstime.com
    electrical equipment and material
    This approval includes the first-time recognition on a federal level of the new job classification of Electrical Testing Engineering Technician.
    Courtesy of NETA
    plant_motor
    Using PF and PF testing techniques to guide electrical testing, maintenance, and asset replacement planning and decision-making

    Sponsored