An existing corporate data center is concerned about possible loss of power due to the fact that it is supplied by only one service. The existing feed consists of a 1600A, 208Y/120V, 3-phase, four-wire service. Data center management personnel propose to add an additional service.

Q. An existing corporate data center is concerned about possible loss of power due to the fact that it is supplied by only one service. The existing feed consists of a 1600A, 208Y/120V, 3-phase, four-wire service. Data center management personnel propose to add an additional service. What are the Code-compliant options available to the data center management team?

A) An additional service cannot be added; this is a violation of 225.30.

B) An additional service can only be added if the capacity requirements exceed 2000A.

C) An additional service can only be added if it is of different characteristics. For example, it is a single-phase, 240/120V, 3-wire service.

D) An additional service identical to the existing service may be installed for “enhanced reliability.”

Answer: D

Explanation: Per a change to 230.2(A)(6) of the 2005 NEC, an additional service per 230.2(A)(6) or an additional feeder per 220.30(A)(6) may be installed for the purpose of “enhanced reliability.” The additional service or feeder may be identical to the existing service or feeder.

Owen is the owner and president of National Code Seminars and the holder of master electrician certifications in 46 states. He can be reached at [email protected].

About the Author

Steven Owen

Voice your opinion!

To join the conversation, and become an exclusive member of EC&M, create an account today!

Sponsored Recommendations

8 Types of Electrical Conduit and Their Uses

Electrical conduit is a tube or raceway used to house and protect electrical wires within a building or structure. From data centers to underground subways to ports and bridges...

A Powerful Duo: Fiberglass conduit and solar applications

Learn how strong, durable fiberglass conduit excelled in an environment with dense cable and helped make a complex burial much simpler for the contractor to help this customer...

How to Calculate Labor Costs

Most important to accurately estimating labor costs is knowing the approximate hours required for project completion. Learn how to calculate electrical labor cost.

Champion Fiberglass® Conduit Protects Cabling For New York's First Offshore Wind Farm

Learn how fiberglass conduit supported a heavy cable load and a buried installation to help this project reach a successful outcome.