True or False?
Question: Raceways installed below metal roof decking must be installed at least 1-½ in. below the lowest point of the metal decking.
See the answer below.
Answer: False
Explanation: While it is true that Sec. 300.4 (E) requires raceways, cables, or boxes to maintain a 1-½ in. clearance from the lowest point of the metal decking, there is an exception that permits rigid metal conduit (RMC) and intermediate metal conduit (IMC) to be installed less than 1-½ in. from the lowest point of the decking. Therefore, the correct answer is false.
Lupacchino is a senior design engineer with Gaylor Electric, Inc. in Noblesville, Ind. and serves as an alternate on NEC Code-Making Panel No. 3. He is currently licensed in more than 80 jurisdictions. He can be reached at [email protected].